Dropped Object Canopy Removal

Location

Forth Road Bridge

Client

Balfour Beatty Civil engineering

Date commenced on site

Mar '13

Duration

5 Weeks

Accidents/Incidents

0

Recycling Rate

96%

Value

£72,000 [Including Credits]

Background

George Beattie & Sons Ltd were contracted as subcontractors to the principal contractor to dismantle the Dropped Object Canopy of the bridge

The construction was primarily structural steelwork with polystyrene protective panels

Specification

  • Dismantle and remove structural steelwork to Dropped Object Canopy of bridge
  • Working at height above "live" traffic necessitating traffic contra flows and in some instances road closures
  • Extremely tight time constraints imposed

Achievements & Successes

All works to be completed in the midst of a very inclement weather, working at height taking into account the natural sway and bounce of the bridge.
George Beattie & Sons Ltd were required to dismantle the structural steel above a steady stream of traffic

 

 


Professional memberships Demolition Contractors Association Accredited Site Audit Scheme - National Federation of Demolition Contractors Constructonline TUV ISO 9001, iSO 14001, BS OHSAS18001 Scottish Building Federation National Demolition Training Group (NDTG) Scottish Plant Owners Association (SPAO) Considerate Constructors Scheme Safecontractor Approved