5-11 Kyle street,
Ayr,
KA7 1RS
Langmuir & Hay
16th April 2021
9 weeks
95%
we were invited to tender for the demolition of the dangerous building on the busy ayr high street making way for the redevelopment of the site.
Stage 1
all services conected to the building will be disconnected and a footpath closure will be put in place on kyle street from blacks shop to debenahms to allow a safe exclusion zone for the demolition works. a fully boarded scaffholding will also be errected to allow hand demolition works to progress.
Stage 2
operatives will then enter the structure and backprop to allow a full internal soft strip to take place removing all material out of the building and into 40yrd skips
Stage 3
operatives will then proceed to hand demolish the roof into the footprint of the building removing materail at an ongoing basis, the will also create a air gap between our property and the adjoining two properties to allow hand demolition of the front facade down to 1 storey.
Stage 4
with all hand demolition works avaliable from the scaffholding complete the scaffholding will be disassembled and a cherry picker will be brought to site to allop operatives to reach areas of walls to be hand demolished.
Stage 5
our 20t Demolition specification excavator will then be brought to site working around local traffic restrictions to remove material into tippers to be brought back to our yard and made into 6f2 to be reused on future projects.
Stage 6
the excavator will then proceed to demolish the remaining rear buildings while continuing to remove all material from site. the area will then be graded and plant demobilise from site.
Stage 7
the gable walls of the adjoing properties will have all openings bricked up and the gabe strap and sheeted to make wind and watertight.
Plant onsite
Site Personell